Top News

Energy Minister Bright Msaka says Malawi has embarked on Rural Electrification Programme Phase 8

6 Min Read

The Rural Electrification Programme started in the 1980s with Electricity Supply Corporation of Malawi (ESCOM) Ltd as the implementing agent using donor and own resources. Since 1980, three phases of the Malawi Rural Electrification Programme (MAREP) were implemented by ESCOM Limited.

 

Following the reforms in the electricity sector, ESCOM Ltd was commercialized and mandated to operate as a commercial entity. ESCOM Ltd could then not continue implementing MAREP since most MAREP projects were deemed not economically viable.

 

 

Faced with the obligation to provide social services to the rural communities, Government took over the responsibility of MAREP and the Ministry of Natural Resources, Energy and Mining, through the Department of Energy Affairs (DoEA) was mandated to plan and implement the Programme.

 

In 2004 the Government of Malawi approved Energy Laws, including the Rural Electrification Act. Through this Act the Energy Fund, which finances MAREP, was created. Sources of this Fund are levies from all energy sales including petroleum products and electricity sales. The Rural Electrification Management Committee (REMAC) was also established with membership from representatives of the Board of Engineers, Society of Accountants of Malawi, Ministry of Local Government, Ministry of Finance and Economic Development and Ministry of Natural Resources, Energy and Mining which chairs the committee. REMAC provides policy and an oversight to the implementation of MAREP.

 

Selection Criteria for MAREP Sites

 

The selection of sites for MAREP is based on a Rural Electrification Master Plan which was concluded in 2004 with financial and technical support of the Japanese Government. The Plan is founded on a three point criteria. The first element of the criteria requires that MAREP activities must focus principally on the electrification of Trading Centers. The second element of the criteria requires MAREP to follow a strict equity principle where all Districts in the country stand equal to each other, irrespective of their population size or level of electrification. The third component of the criteria requires that for objectivity in site selection, targeted Trading Centers in each District be based on a rational ranking process following known economic sub-criteria. Currently, this sub-criterion is based on the potential demand of each Trading Centre, which is invariably linked to the level of economic activities.

 

MAREP Phases Implemented

 

The Government of Malawi, through the Department of Energy Affairs, has implemented four phases between 2002 to date as follows:

• Phase 4 planned to electrify 58 centres, however, 39 other centres benefited at a total cost MK680.2 million. This was implemented between 2002 and 2007

.

• Phase 5 planned to electrify 27 centres, one per district except Likoma which is fully electrified. Implementation of this phase was from September 2007 to February 2009 at a total cost of MK899 million.

 

• Phase 6 planned to electrify 54 centres, two per district but ended up electrifying 91 Trading Centres. Implementation of this phase was from November 2010 to August 2012 at a total cost MK2.4 billion.

 

• Phase 7 targeted 81 centres, three per district.

 

Implementation started in August, 2013 and is still under way and will have electrified 139 Trading centres by the time it is completed this year. The total cost of this phase is expected to be at MK8.3 billion.

 

MAREP Phase Eight

 

My Ministry is currently in a process to implement MAREP Phase Eight. Like any other MAREP Phase, this one too is targeting Trading Centres which have been selected from the Rural Electrification Master Plan.

 

MAREP Phase Eight will target 81 Trading Centres, three from each District

 

The list of centres for MAREP Eight is available in my Ministry for you.

 

Planning of Phase Eight started in May and is expected to be completed by end of August 2015. The output of this planning exercise will be Bills of Quantities of materials required to implement the phase. Procurement process of the materials will start in September 2015 and is expected to be finished by February 2016. Alongside this process, procurement of contractors will also be done. It is expected that construction works will begin in March 2016 and finish in March 2017. MAREP Phase Eight is estimated to cost about MK12.1 Billion.

 

Challenges Associated with the Selection Criteria

 

The overarching challenge to rural electrification is finances and capacity. With only installed capacity of 351.75 MW of electricity in the country, it is impossible to electrify each and every deserving Trading Centre, since MAREP draws its power from this installed capacity on national grid. More power is, therefore, required to reach out to all deserving Trading Centres.

 

Additionally, demographic, geographic and economic disparities also pose a huge challenge to the successful implementation of the programme. This is so because some Districts have huge population densities than others, some are growing faster economically than others meaning they have a lot more Trading Centres than others.

 

Measures to Address Some of the Challenges

 

The Government is committed to increase electricity capacity through involvement of Independent Power Producers (IPPs). IPPs have been invited to generate electricity and inject it into the national grid through Power Purchase Agreement (PPA) with ESCOM. This is expected to increase the power capacity nationally, which will be extended to MAREP, thereby increasing the number of Trading Centres to be electrified.

In addition to this, my Ministry intends to put in place measures to ensure that highly populated Districts with higher economic growth potential are prioritized to have an increased number of targeted Trading Centres. This would require to use scientific targeting methods to include demographic, geographic size, electricity demand and the level of electrification.

 

Conclusion

 

The Government of Malawi is committed in improving the life of the population in rural areas by providing electricity throughout the country. Although there are challenges in power generation capacity, financial resources and selection of sites that would ensure equity, my Ministry is working hard to find lasting solutions to these challenges.

 

NO. DISTRICT TARGETTED TRADING CENTRE

1 Chitipa 1 Sokola

2 Mahowe

3 Namatumbi

2 Karonga 4 Chesa

5 Ngana

6 Mwangulukulu

3 Rumphi 7 Luviri

8 Phoka

9 Bowe

4 Mzimba 10 Bulala

11 Emfeni

12 Khosolo

5 Nkhatabay 13 Chituka

14 Nthungwa

15 Chisu

6 Kasungu 16 Nthabuwa

17 Chambwe

18 Ndonda

7 Nkhotakota 19 Mpondagaga

20 Katimbira

21 Malowa

8 Ntchisi 22 Mawiri

23 Malambo

24 Bumphula

9 Dowa 25 Mkukula

26 Kalumbu

27 Kachigamba

10 Salima 28 Chitala

29 Chinguluwe

30 Michulu

11 Lilongwe 31 Mtema

32 Malembo

33 Chadza

12 Mchinji 34 Kazyozyo

35 Kabuthu

36 Kalulu

13 Dedza 37 Mphunzi

38 Kamenya

39 Mphathi

14 Ntcheu 40 Kandeu

41 Chilobwe

42 Mphepozinai

15 Blantyre 43 Mitsidi

44 Chigwanjwa

45 Domwe

16 Chiradzulu 46 Ndunde

47 Msoni

48 Chikaonda

17 Thyolo 49 Chipho

50 Sandama

51 Mphuka

18 Mulanje 52 Nakamba

53 Milonde

54 Mzizira

19 Phalombe 55 Dzenje

56 Mpasa

57 Namba

20 Chikwawa 58 Changoima

59 Dolo

60 Thendo Border post

21 Nsanje 61 Msiyakhuni

62 Chibuli

63 Kanyimbi

22 Mangochi 64 Kwisimba

65 Manjuni

66 Mvumba

23 Balaka 67 Shire North

68 Kuntiyani

69 Sawali

24 Machinga 70 Malundani

71 Nayuchi

72 Mangamba

25 Zomba 73 Ngondole

74 Makina

75 Nachuma

26 Mwanza 76 Njolomola

77 Chipondeni

78 Ilemba

27 Neno 79 Chilimbondo

80 Kasamba

81 Kundembo

Maravi Post Reporter

Op-Ed Columnists, Opinion contributors and one submissions are posted under this Author. In our By-lines we still give Credit to the right Author. However we stand by all reports posted by Maravi Post Reporter.


Discover more from The Maravi Post

Subscribe to get the latest posts sent to your email.

Discover more from The Maravi Post

Subscribe now to keep reading and get access to the full archive.

Continue reading